OUA outlines multi‑phase plan to replace septic systems on Treasure Island

Oct 22, 2026

OUA says Treasure Island will be connected to sewer in three phases, with phase‑1 design ~90% complete; the utility cited prior sampling that found nutrient and artificial‑sweetener signals tied to septic leachate and said more than $20 million in grants have been obtained so far.

The full story

Greg Kennedy told commissioners the Treasure Island septic‑to‑sewer effort is an extensive multi‑phase project designed to remove nutrient loads from near‑shore septic systems. "So in total, we're gonna have near 2,000 homes to connect from, you know, remove septic systems and connect to the sewer," Kennedy said, explaining the environmental motivation and noting the project is broken into phases with phase‑1 design at about 90%.