Engineer reports delayed asphalt and immediate drainage fixes at Eagleview Village

Oct 16, 2025

Will Owen told Council topsoil backfilling and overseeding at Eagleview Village will start within 7–10 days to help drainage; the final asphalt lift is delayed until Comcast reroutes fiber optics, which he said he does not believe will finish until spring.

The full story

City Engineer Will Owen walked Council through four areas of concern at Eagleview Village. He said backfilling the gazebo area and open space with topsoil will begin in the next 7 to 10 days and that overseeding will occur concurrently to improve vegetation and assist drainage.