Engineer reports delayed asphalt and immediate drainage fixes at Eagleview Village
Oct 16, 2025
Oct 16, 2025
Will Owen told Council topsoil backfilling and overseeding at Eagleview Village will start within 7–10 days to help drainage; the final asphalt lift is delayed until Comcast reroutes fiber optics, which he said he does not believe will finish until spring.
The full story
City Engineer Will Owen walked Council through four areas of concern at Eagleview Village. He said backfilling the gazebo area and open space with topsoil will begin in the next 7 to 10 days and that overseeding will occur concurrently to improve vegetation and assist drainage.