Appleton approves $111,111.90 final payment for library roof after change-order reduction
Jun 10, 2026
Council approved final payment of $111,111.90 for the Appleton library roof replacement after a contractor change order was amended from $42,786.65 to $32,786.65; total project cost reported as $189,511.90. Final payment is contingent on receipt of form IC134.
The full story
Administrator John Olinger told the council the library roof replacement is complete and outlined why the project exceeded initial expectations: the center of the building lacked insulation, requiring additional insulation and a vapor barrier; contractor work also added six downspouts and collector boxes to prevent erosion at roof edges. The contractor submitted a change order initially for $42,786.65; Olinger said he negotiated that down to $32,786.65 and reported a total project cost of $189,511.90.