Design schedule, contractor and historic-review plan set for Tennessee Residence update
Aug 19, 2026
Aug 19, 2026
The design team reported a target construction start of early February 2027; the Historical Commission will provide technical support and Reeves and Young is the contractor using a CM/GC delivery method.
The full story
The design team reported that the current schedule targets construction start in early February 2027, and commissioners were told that design decisions need to be complete by the end of the year. Beth Meadows said the subcommittee review and approval timeline is expected to allow final design decisions by year-end, though decisions about the first family’s move-in could affect sequencing.