Engineers present three task orders for water and wastewater work
Nov 9, 2022
Nov 9, 2022
Strand Engineers presented three task orders covering Well No. 2 rehabilitation, a Source Water Protection plan, and a Wastewater Treatment Plant capital improvements plan; trustees received details and supporting packets.
The full story
Ryan Wood of Strand Engineers briefed trustees on three proposed task orders: rehabilitation of Well No. 2, development of a Source Water Protection plan, and a Wastewater Treatment Plant Capital Improvement Plan. Wood distributed materials and described the scope of each task so the Village could consider contracting or scheduling the work.