President Bank outlined a proposed amendment to task order 23-01 (raise from $16,800 to $18,800) and introduced a new task order 24-01 for a sanitary-sewer smoke test priced at $60,000; both items are scheduled for formal votes May 28.

The full story

Village President Bank told trustees that Strand Engineers has requested an amendment to task order 23-01 to increase the budget from $16,800 to $18,800. He also presented task order 24-01, a proposed sanitary-sewer smoke test, with a quoted amount of $60,000. Both items were presented as proposals to be taken up at the May 28 business meeting.