Village consultant reports Main Street application submitted, permit work ongoing
Nov 16, 2015
Nov 16, 2015
Blanchard Design Associates reported the Public Works application for Main Street has been submitted (feedback expected in February); engineers also reworked the NPDES brine-disposal permit, and parking lot and tank plans are due to be returned this week.
The full story
Fahy of Blanchard Design Associates told council that the Public Works application for Main Street had been submitted and that the village should receive feedback in February. Fahy also said a reworked NPDES (noted in transcript as NPOES) water permit for brine disposal had been completed, parking-lot and tank plans were returning this week, and AEP had moved a pole near the new village sign.