How PG&E will pick circuits: four‑screen selection, thresholds and prioritization
Nov 2, 2026
PG&E explained a four‑screen project acceptance framework (eligibility, desktop comparison, scoping, prioritization) and listed numeric thresholds and portfolio standards that determine whether a circuit advances toward undergrounding.
The full story
PG&E described a four‑screen project acceptance framework used to move circuit segments from eligibility to confirmed projects and portfolio prioritization. Screen 1 identifies eligible segments by location (HFTD tiers 2 or 3 or fire rebuild areas) and whether they meet at least one risk threshold. Screen 2 is a preliminary desktop comparison of undergrounding versus alternatives (overhead hardening, remote grid, hybrids). Screen 3 tests desktop results against scoping, constructability and local factors to confirm mitigations, and Screen 4 ranks confirmed projects primarily by monetized overall utility risk reduced per primary overhead mile removed while allowing adjustments for rebuild needs and community impacts.