Board approves $84,528 contract amendment for Gresham Women's Shelter ventilation project
Oct 30, 2026
Oct 30, 2026
Multnomah County approved an $84,528 contract increase for the Gresham Women's Shelter ventilation project after contractors discovered unforeseen structural and moisture damage that required additional remediation and permit work; funding is available in the facilities capital improvement fund.
The full story
The Multnomah County Board voted to approve an $84,528 increase to the construction contract for the Gresham Women's Shelter ventilation project to address unforeseen structural and moisture issues discovered during initial construction inspections.
