Contractor seeks $49,102 payment after disputed extra excavation on Safe Routes to School project

Feb 24, 2026

Jeff Kobliska of Ideal Construction asked the Verndale council to pay $49,102.19 for sidewalk work on the Safe Routes to School project, saying engineers told him to continue after excavation exceeded planned quantities; City Clerk Melissa Current said Moore Engineering recommended withholding the overage as it was the contractor’s decision. Mayor Tara Erckenbrack asked staff to schedule a meeting with Moore Engineering before the March 9 council meeting to resolve the dispute.

The full story

Jeff Kobliska of Ideal Construction asked the Verndale City Council on Feb. 24 for payment of $49,102.19 for work completed on the Safe Routes to School sidewalk project. Kobliska said most items in the contract were unit-priced and that Class 5 material had been a planned quantity.