Officials say school building program remains within available financing
Nov 3, 2026
Project managers told the council the combined school program remains within available funding — with about $174.1 million contracted and anticipated costs (excluding contingencies) of roughly $197.2 million against available funding of $203.5 million — and staff said projected reimbursements from RIDE are subject to state rules.
The full story
Project manager Colin McCarthy presented a budget update for the town's school construction program, saying available funding stood at $203,501,162 (including roughly $190 million in bond funds, bond interest and premium, a NEVI grant, welding shop grants and a general-fund appropriation). He listed project budgets: Middletown Middle–High School $174,690,200; Valley Elementary $20,182,100; Forest Ave Elementary $8,300,000.