Steve Miller of Main Street said CenterPoint would not allow attachments, forcing a mostly underground fiber design with limited aerial sections; he offered to coordinate potholing/locates and restoration standards with local utilities and government affairs staff.

The full story

Steve Miller, who identified himself during the meeting as engineering supervisor for Main Street, presented the company's revised plan for a broadband rollout and explained why the project will be primarily underground.

"Unfortunately, they came back with us that their rollout was that we could not attach to," Miller said, describing CenterPoint's decision not to allow attachments. As a result, Miller said his team redesigned the route to include a "significant amount of underground" construction with a few aerial segments and several road crossings; he listed specific crossings including West Cherry Street, Perrigo, Indiana, and West Cherry behind houses between Indiana and Central.

Miller told the board the team tried to minimize road crossings and that construction leadership has changed since the last rollout; he said the company will call locates and work with local utilities on restoration. He also identified Mike Wilson from his government affairs team as the contact for agreements and asked the board to share restoration requirements so Main Street can include them in the construction contract.

Board members pressed for commitments on potholing, locating existing utilities and repairing any settling or damage to town roads; Miller said Main Street will work with Mike Wilson to address those points and welcomed a follow-up meeting with board members and staff. The board did not vote on project approval at the meeting but discussed next steps including legal review of permitting and restoration obligations.