Engineer: rain delays grading; Winslow Road bridge replacement proceeding
Sep 22, 2026
Sep 22, 2026
County Engineer Cathy Nicholas reported that recent rain has made gravel roads too soft for graders, crews are preparing for winter and Taylor Construction's replacement of the Winslow Road bridge is progressing; she also said one reopened bridge required additional riprap work.
The full story
County Engineer Cathy (Cathy/Catherine) Nicholas updated the board on road conditions and a bridge replacement project. She said gravel roads were soft after recent rain and motor graders could not be out on the gravel system, but crews hope to resume when weather permits and will begin winter prep including spot rock and blading as needed.