Committee approves KL Engineering Amendment #2 after scope clarification and a $12,100 add
Apr 13, 2026
Apr 13, 2026
The committee approved Amendment #2 to KL Engineering's contract, which removes a '2026 pathways if authorized' section, adds $12,100 for easement exhibits and a 60% design submittal, and shifts MetroNet coordination costs to MetroNet.
The full story
KL Engineering presented Amendment #2 to its village contract, and the committee approved it after clarifying scope changes and cost impacts. Mr. Brush explained the amendment removes the entire "2026 pathways if authorized" section of the contract while adding $12,100 for easement exhibits related to 1255 Highland and for unanticipated 60% design submittal work that had not been in the original 30%/90% submittal schedule.