Engineer: WWTP improvement paperwork complete; summer construction expected

May 7, 2026

The village's WWTP engineer told trustees all paperwork has been submitted, EPA requested annual audits and approved recent checks; construction is expected to start in summer with a potential first-month pay request.

The full story

Mr. Patel, the engineer on the wastewater treatment plant (WWTP) improvements project, told the Village Board on May 7 that "All paperwork has been sent. EPA asked for audits, they will do this annually. All eternal checks from EPA approved last week. There will be a summer start date, with a pay request possibly first month of start of project." The board recorded the update; no vote was required.