Board notes incomplete items at CCJJC final completion; authorizes intercom and panic buttons

Feb 20, 2024

County staff and the contractor reported the CCJJC Phase 2 final completion date of Jan. 19, 2024 was not met; the Board authorized an intercom system and additional panic buttons while other items remain outstanding, including landscaping, irrigation and software fixes.

The full story

Owner representative Hal Hutchinson and representatives from GSG Architecture and Sampson Construction briefed the Board on outstanding items at the Converse County Justice and Juvenile Center (CCJJC). The minutes record that "Final completion date was January 19, 2024, which was not met; landscaping and irrigation are excluded from this requirement." Remaining items include detention housing work, certain software issues, irrigation and landscaping, uplighting, drainage and owner training. Delay days, warranty extensions and security system requests were discussed.

Free newsletter

Sign up to keep reading.

Your free newsletter brings you what your city council, county, and school board discussed and decided.

or
Already have an account? Sign in