Cell 7 construction progressing; contractor reports 150,000 cubic yards remaining

Apr 23, 2026

Norm Strickland updated the board on Cell 7 construction: crews have reduced remaining soil from 240,000 to about 150,000 cubic yards, are installing interceptor trenches and drainage materials, and are conducting moisture/compaction testing ahead of subsequent liner and cover work.

The full story

Norm Strickland provided the board with a construction update on Cell 7, reporting that site earthwork progress has reduced remaining soil volumes from previous figures and that crews are installing interceptor trenches and drainage materials in preparation for final subgrade and liner placement.