Utilities outline pipe‑replacement progress and plan to address low water pressure

Aug 3, 2026

Utility leaders reported completion of much of phase 1 of an extensive pipe‑replacement program, described change orders to improve pavement restoration, and said work to tie in a new 36‑inch main should ease pressure problems by autumn; crews are monitoring temporary PRV bypasses now affecting some neighborhoods.

The full story

City utilities staff updated council on the multi‑phase pipe‑replacement program that aims to replace roughly 90,000 linear feet of aging distribution pipe across phases. Phase 1 has replaced about 42,000 feet of pipe; phase 2 (≈41,000 ft) is underway and staff said they are pushing for full‑width milling and overlay to avoid a patchwork final product.