Resident says unpermitted parking‑lot work created drainage, code problems

Sep 9, 2025

A resident told council an adjacent business expanded a parking lot without permits, 8‑1‑1 utility locates or proper surfacing, and she cited borough code chapters she said were violated; staff said code enforcement inspected and will follow up. The council asked staff to continue investigations.

The full story

A resident described an ongoing dispute over a newly expanded parking lot that she says began on July 4, 2023. The speaker told council the developer "dug a full, very fox into my backyard, filling it in with gravel" and that "no permit was issued prior to digging" and "no 8 1 1 call date prior to digging." She also said no drainage or proper surface material was installed.