Council authorizes guaranteed maximum price amendment for Community Center Phase 2
Oct 19, 2026
Oct 19, 2026
Council adopted Resolution No. 26-138 authorizing a guaranteed maximum price amendment for the Maple Grove Community Center Renovation and Expansion Phase 2, with staff reporting an estimated total project cost just under $80 million and identified value-engineering savings of approximately $4.01 million.
The full story
Public Works/Engineering Director Chris LaBounty presented the Phase 2 Community Center Renovation and Expansion (Project No. 26-21), describing scope, schedule, and cost estimates. "The total estimated project cost for Phase 2 is just under $80 million," LaBounty said, and staff told council initial bids were around $70.5 million with a pre-value-engineering estimate of $71.2 million.