Staff reports show multi-year delays and developer changes on local solar projects
May 12, 2026
Planning staff said Daisy Lane Solar and Davis Hill remain pending after about a year; the Gibson Solar Project has a new developer (Hanwha Group) planning a scaled-down resubmission; battery storage also discussed as emerging land-use applications.
The full story
Planning staff told the commission on May 12 that several solar-related land-use cases remain pending. Staff said the Daisy Lane Solar application has been delayed by access issues and has been pending for almost a year; Davis Hill also remains unresolved after about a year. Staff told the commission that the Gibson Solar Project has been sold to a different developer and that Hanwha Group plans to take over, scale the project down and resubmit after the project was denied by the board last July.