County engineer updates board on four bridge and road projects

Feb 19, 2026

County Engineer Justin Hastie told the Gallatin County Board that the Peabody bridge design is 95% complete but awaiting State Historic Preservation Office review; Ridgway plans were revised to a double culvert and the Asbury (Downen Road) bridge secured IDOT preliminary approval. Shawneetown blacktop safety-shoulder design is targeted for FY2028.

The full story

County Engineer Justin Hastie briefed the Gallatin County Board on multiple transportation projects on Feb. 19. He said the Peabody Haul Road Bridge Replacement design is 95% complete but remains held up in a 30-day comment period with the State Historic Preservation Office. "The Peabody Haul Road Bridge Replacement design is 95% complete. Still held up with the State Historic Preservation office, in the 30-day comment period," Hastie reported.

Hastie also described a revision to the Ridgway Township project from a bridge to a double culvert to increase the waterway opening without changing road height, noted that Asbury Township's Downen Road bridge received IDOT approval of the preliminary bridge design and hydraulic report, and said ROW documentation is in preparation. He added that the Shawneetown New Haven blacktop safety-shoulder design is being expedited for a potential election-year funding opportunity with plans targeted for FY2028 and a May 1 plan-completion goal.

Written with AI from the event video and transcript. Check it against the source ↓