County engineer updates board on four bridge and road projects
Feb 19, 2026
County Engineer Justin Hastie told the Gallatin County Board that the Peabody bridge design is 95% complete but awaiting State Historic Preservation Office review; Ridgway plans were revised to a double culvert and the Asbury (Downen Road) bridge secured IDOT preliminary approval. Shawneetown blacktop safety-shoulder design is targeted for FY2028.
The full story
County Engineer Justin Hastie briefed the Gallatin County Board on multiple transportation projects on Feb. 19. He said the Peabody Haul Road Bridge Replacement design is 95% complete but remains held up in a 30-day comment period with the State Historic Preservation Office. "The Peabody Haul Road Bridge Replacement design is 95% complete. Still held up with the State Historic Preservation office, in the 30-day comment period," Hastie reported.