Council authorizes water-project change orders totaling a net decrease, approves Kevin to sign

Sep 28, 2026

Centerville approved two water-project change orders: a $245,060.45 decrease after finding fewer lead lines and a $90,818.50 increase to remanufacture a well house. Council authorized staff to sign both change orders.

The full story

Town staff told the council that two change orders for the ongoing water project will net a decrease overall after field work and design adjustments. Kevin reported Change Order 1 reduces project cost by $245,060.45 because fewer lead lines were found than anticipated. Change Order 2 adds $90,818.50 to remanufacture a well house. Kevin asked the council to authorize him to sign both change orders.