Council approves engineering contract amendment for Ravalli/Valley Street; transcript shows inconsistent amounts

Aug 18, 2026

Council approved a closeout amendment to an engineering contract for the Valley/Ravalli Street project tied to delays, unsuitable soils and additional inspection time; the transcript records conflicting dollar amounts, which staff should verify against the contract document.

The full story

The Hamilton City Council approved what staff described as a closeout amendment to an engineering contract related to the Valley/Ravalli Street project on Aug. 18, citing contractor delays, unsuitable soils encountered during construction and extra engineering inspection time.

Staff said the project had been partially funded by a House Bill 355 grant, which triggered Montana Environmental Policy Act review requirements. The mayor read a number in the meeting: “for the amount of $6,028,891 and 85¢,” but the motion language recorded and the clerk’s motion referenced a much smaller figure later in the discussion: “not to exceed $28,891.85.” Council voted to approve the amendment as presented. Because the transcript includes inconsistent dollar figures and multiple spellings for the engineering firm (transcript variants: “WGN,” “WGM”), reporters and records staff should verify the approved amendment amount and the final contract language in the official contract document.

Staff characterized this item as a closeout change order that addresses liquidated‑damages time, subcontractor delays and additional engineering inspection work; councilors recorded the vote and moved to the next agenda item.