River Ridge approves $3,500 to widen E3 Basin control structure
Mar 24, 2026
Mar 24, 2026
The board approved MRI Construction Proposal #606 for $3,500 to widen the weir at the E3 Basin control structure to maximize outflow; staff will provide before‑and‑after photos and consider a manual gate.
The full story
On a unanimous vote the board approved MRI Construction Proposal #606 to widen the E3 Basin control‑structure opening for $3,500. Cleo Adams, District Manager, presented the proposal and the motion was made by Kurt Blumenthal and seconded by Bob Schultz.