Agent flags nonconforming stream work, marsh float storage and National Grid tree work

Nov 5, 2026

Conservation Agent Charlotte Peckel reported on a problematic stream relocation at 3A that DEP asked to be reworked, said work on the Black Horse Lane water main is progressing with replication to follow, and warned property owners that storing floats on the marsh is not allowed and may lead to enforcement if educational outreach fails.

The full story

Conservation Agent Charlotte Peckel briefed commissioners on several enforcement and project updates. She said a contractor's stream relocation at the 3A improvement project did not follow DEP's expectation for naturalized stream features and will need to be redone to meet permit conditions. Regarding Black Horse Lane, she said the water main loop is connected, but replication work will be scheduled in the spring pending financial and logistical coordination with the water commission.