Consultant says Springfield rail-link work is 60% complete; 3rd Street corridor eyed for redevelopment

Nov 5, 2026

Hanson consultant Mike Mendenhall told the council the 10th Street corridor rail-shift is on track for completion around end of 2027, with five of six segments finished and funding in place for some pieces; the freed Third Street corridor is being planned for public-realm redevelopment.

The full story

Mike Mendenhall of Hanson gave the council a progress report on the Springfield Rail Improvements project tied to the 10th Street corridor, saying construction is on schedule and that moving the Third Street tracks to 10th Street will free the Third Street corridor for redevelopment. "Overall it's about sixty percent complete so we're on track to be done here in about a year," Mendenhall said.