Committee outlines CPC funding and RFP timeline for bridge work

Nov 6, 2026

Members reviewed a CPC request of roughly $450,000–$500,000 and a procurement timetable that requires a March decision to keep appropriation and RFP timing on track; award would be restricted until funds are appropriated on July 1.

The full story

Committee members described the funding path and procurement schedule for potential bridge work. S1 said the Community Preservation Committee request is "roughly a five, 450 or 500,000," and members explained that CPC appropriation timing affects when an RFP can be issued and when contracts can be awarded.