Committee recommends $30,000 study for Turtle Creek drainage problem
Oct 26, 2026
Staff asked the committee to recommend city council approve $30,000 to survey and study drainage at 224 West Memphis Street in the Turtle Creek subdivision; committee members expressed concern about public benefit but approved the recommendation after applicant testimony describing chronic yard flooding.
The full story
Staff presented a request to recommend city council authorize $30,000 for a survey and drainage study at 224 West Memphis Street in the Turtle Creek subdivision. Sarah Walters, the Stormwater Project Manager (speaker 6), said the site drains from more than four lots, that the subdivision was platted in 1976 before current engineering criteria, and that the drainage area appears to be just under an acre. Staff recommended funding a study to determine whether a mitigation solution is feasible.