Selectboard approves $6,000 change order for additional culvert discovered on Spring Hill Road
Nov 2, 2026
Nov 2, 2026
After crews found a failed 12‑inch culvert adjacent to an 18‑inch replacement, the Selectboard approved a $6,000 Sanderson Trucking change order to cover the unanticipated work.
The full story
Town staff reported the Spring Hill Road culvert project is near completion but crews discovered an additional failed 12‑inch culvert near Chaves Road and Little Pond Road that required replacement alongside an 18‑inch culvert already scheduled for work.