Commissioners confirm INDOT-backed plan to widen 400 N at SR 3, set August start
Aug 3, 2026
INDOT accepted designs and permits for widening the 400 N and SR 3 intersection using prefab 'bridge jumpers.' Commissioners discussed closures, escort procedures, pre-move video documentation for reimbursements, and INDOT NOS approval requirements; work is targeted to begin around Aug. 13 for about three weeks.
The full story
Commissioners reported that INDOT has accepted the designs and permits for the intersection-widening project at 400 N and SR 3; the plan calls for installing prefabricated bridge decks ('bridge jumpers') to avoid loading existing bridge structures. The project was described as targeting an August 13 start with an approximately three-week installation window, during which closures will allow only local traffic, emergency services and school buses.