Road closures and bridge work set for October as crews adjust for harvest
Sep 19, 2026
Sep 19, 2026
County crews will remove temporary bridge jumpers to allow farm equipment during harvest, reinstall jumpers Oct. 6–9 for a last superload, and close the County Road 350 West intersection Oct. 6–15; U.S. 421 structure work targets completion in October.
The full story
County highway officials told commissioners that crews planned to remove temporary bridge jumpers the morning of Sept. 21 to permit farm traffic during harvest. The jumpers will be reinstalled for one day around Oct. 6–9 for a final superload, then removed again. The action is intended to balance harvest movement with remaining heavy-haul needs.