Decatur County adopts temporary moratorium on hyperscale data-center applications

Sep 19, 2026

The county adopted Ordinance 2026-15 on Sept. 21, 2026, pausing acceptance and review of applications for data centers with an aggregate critical IT load of 250 megawatts or greater through Dec. 31, 2026, to allow plan updates and drafting of local standards.

The full story

Decatur County commissioners on Sept. 21 adopted Ordinance 2026-15, a temporary moratorium on acceptance, processing, review and filing of applications for data centers with an aggregate critical IT load of 250 megawatts or greater. The moratorium took effect Sept. 21, 2026, and runs through Dec. 31, 2026, at 5 p.m.; properly presented petitions and applications submitted before enactment are exempt.