County approves $870,072.49 amendment for Fairgrounds Phase Two; no tax impact

May 4, 2026

Commissioners approved a Build-Operate-Transfer amendment adding $870,072.49 to the Fairgrounds Phase Two budget, bringing the project total to $4,541,295.27; the phase will be funded by donations and in-kind contributions totaling over $130,000, with no additional tax impact, and the motion carried unanimously.

The full story

The Decatur County commission voted to approve an amendment to the Fairgrounds Phase Two Build-Operate-Transfer agreement that increases the scope and cost of the phase by $870,072.49, bringing the total project cost to $4,541,295.27.