Council asked to approve ~ $312,000 drilling change order and schedule extension for Dixie Well

Nov 10, 2026

Engineering asks the Council to approve Change Order No. 1 with Hydro Resources for the Dixie Well drilling project to address unstable subsurface conditions, requesting an additional $312,134.25 and a 56‑day contract time extension with a new substantial completion date of Feb. 1, 2027; the work is funded by Culinary Water Impact Fees.

The full story

An Engineering staff report asks the City Council to approve additional funds for the Dixie Well drilling contract to Hydro Resources - Rocky Mountain, Inc. due to unforeseeable subsurface conditions.