Developer updates council on Jackson Ridge well and pump testing
Nov 24, 2025
Nov 24, 2025
P. Hill of Woodhaven Building and Development told the council the pump at the Jackson Ridge well is failing; the developer is installing a new pump and has scheduled drawdown and yield tests next week before approval for public use.
The full story
P. Hill, president of Woodhaven Building and Development, updated the council on progress at the Jackson Ridge property. Contractors (Eichelberger from Gettysburg) had pulled the well pump and determined the pump unit was bad; the developer said they will install an entirely new pump and scheduled drawdown and yield tests next week to support public-use approval.