Bridge 63 beams due Sept. 15; county expects roughly $87,000 from FEMA for debris removal
Sep 2, 2025
Sep 2, 2025
Highway Department reported Bridge 63 replacement moving forward with beams scheduled for Sept. 15 and said the county’s FEMA debris-removal application is a 75/25 cost share, yielding an estimated $87,000 from FEMA of a $106,000 project.
The full story
The Decatur County Highway Department reported ongoing maintenance and project updates at the Sept. 2 meeting, including an update that beams for Bridge 63 are scheduled for delivery and installation Sept. 15.