Study highlights Hamby Interceptor as major long‑term sewer project
Nov 10, 2026
Engineering staff told the Planning Commission that the Hamby (East) Interceptor is the largest long‑term collection system project in the draft PFP, phased with development and estimated at over $40 million; smaller near‑term projects focus on pump‑station decommissioning and localized upsizes.
The full story
City engineers told the Planning Commission on Nov. 9 that the collection system work in the draft public facility plan prioritizes gravity‑first design, decommissioning smaller pump stations and building larger interceptors to serve growth. Lisa Connelly of the Engineering Division said the Hamby (East) Interceptor, which would run from 27th and Neff east and north to connect with the northeast interceptor and the WRF, is the largest long‑term project and will be phased by development.
Connelly said the Hamby Interceptor is “over a $40 million project” and that near‑term priorities include smaller upgrades in the zero–five year window (Southwest Sewer Basin, a Shetland Park upsizing) and a possible north‑interceptor extension in years five–ten, depending on development. She emphasized the city’s emphasis on replacing one‑off developer pump stations with gravity lines to reduce long‑term operating costs and standardize infrastructure.
Written with AI from the event video and transcript. Check it against the source ↓