The board discussed next steps for the Eaton parcel RFP after receiving three submissions (two non-responsive). Options included forming an advisory committee with abutters and stakeholders, or placing use restrictions before any sale; the manager said RSA 41:14a public-process rules would apply if the board pursues a sale.
The full story
The Select Board reviewed results of a request for proposals (RFP) for the Eaton parcel and discussed options for the town's stewardship of the property. Manager (speaker 2) said three bids were submitted, two were considered non-responsive and one developer supplied the required financial documentation and a commitment to purchase and develop the site.