Dec 22, 2018
Dec 22, 2018
Board heard estimates of $10,000–$15,000 for a new metal roof at the senior center and directed staff to collect two more estimates and prepare an RFP if selectmen decide to encumber funds before year end.
The full story
Selectmen reviewed three preliminary estimates for the senior center roof repair, which ranged roughly from $10,000 to $15,000 depending on the underlayment and extent of underlying wood replacement. Members agreed they cannot encumber funds until the town has a formal obligation to pay, so staff will obtain additional estimates and prepare an RFP if the board wants bidders to respond within the limited winter window.