Commissioners approve $35,312.25 pay application for fairgrounds READI project
Aug 3, 2026
Aug 3, 2026
The board approved GM Development's pay application for $35,312.25 on the READI fairgrounds project, leaving a remaining balance of $107,080.51; work includes electrical pole removal and communications rerouting, with coordination assigned to Scott Barnes and Commissioner Gabe Nobbe.
The full story
Decatur County commissioners approved a GM Development pay application for $35,312.25 related to the county's READI fairgrounds project. The meeting record lists a remaining project balance of $107,080.51. Work described includes electrical pole removal and communications rerouting; Scott Barnes and Commissioner Gabe Nobbe will coordinate speaker and communication-line work.