TPO previews Mobility Plan 2050 TIP amendments, opens 30-day air-quality public comment

Nov 11, 2026

TPO staff previewed amendments to align Mobility Plan 2050 with TDOT's 10-year plan and the FY26–29 TIP, highlighted major items (Watt Road/Campbell Station interchanges, Alcoa Highway cost increase from $150M to $221M, new Oak Ridge SR-327 realignment), and announced a 30-day public comment period with final adoption expected at the Executive Board on Dec. 16.

The full story

TPO staff provided an informational preview of Mobility Plan 2050 changes and related TIP amendments that will return for formal action next month. Staff said the primary purpose was to reconcile TDOT's 10-year plan with local programming; specific items highlighted included the Watt Road and Campbell Station interchanges (Watt Road being programmed for right-of-way in FY27 and construction in FY28), combining Everett Road widening into the Watt Road project, and a large cost increase for the Alcoa Highway relocation project from $150 million to $221 million.