Commission approves partial undergrounding plan after technical briefings from utilities

Nov 10, 2026

After technical testimony from Farmers Electric and the developer, the Rockwall Planning and Zoning Commission approved a compromise “blue plan” that buries a portion of utility lines but leaves above-ground vaults and switchgear on site. Commissioners pressed for longer-term burying as redevelopment allows.

The full story

The Rockwall Planning and Zoning Commission voted to approve a variance that allows a hybrid utility configuration—the board endorsed the applicant’s “blue plan” that buries a portion of the overhead lines while placing switchgear and vaults above ground on two pads.