100 South reconstruction phase two paving underway; weather may affect final work

Nov 11, 2026

Staff reported phase two of the 100 South reconstruction has received HMA intermediate and crews planned stonework, with final paving contingent on a short window of favorable weather.

The full story

Staff updated the commission on phase two of the 100 South reconstruction, reporting that the segment up to Triads Bird Driveway had received HMA intermediate and that crews had closed up for now but opened again that morning to assess if they could continue. The staff member said they were hoping to do stone work this week and "sneak in some good paving weather next week," noting that cold, wet weather in the coming two weeks could affect paving operations.