SCDOT updates schedules: several Aiken County projects moving toward ROW and construction
Feb 5, 2026
SCDOT reported SC‑126 plan and environmental work are complete and construction is ready pending funding; Bettis Academy and Whiskey Road intersection designs are in preliminary phases with ROW and construction timelines through 2027; Storm Branch bridge replacement expected open mid‑2026.
The full story
Adam Humphries of SCDOT gave a project status update covering multiple projects in the South Carolina portion of the ARTS MPO. He said plan development and environmental coordination for SC‑126 (Belvedere‑Clearwater Road) are 100% complete and the project is ready for construction pending funding. Preliminary design is underway for the Bettis Academy Road at Whaley Pond Road intersection with right‑of‑way acquisition planned in late 2026 and construction targeted for late 2027.
Other project updates included Whiskey Road (SC‑19) at Powderhouse Road intersection improvements (preliminary design ongoing; right‑of‑way planned late 2026, construction late 2027), Shiloh Heights Road pedestrian improvements (approx. 0.5 miles, est. cost $649,000) and Mustang Drive pedestrian improvements (est. cost ~$624,000), and that the Storm Branch Road bridge replacement — a multi‑year effort — is nearing completion with an expected opening by mid‑2026.
Written with AI from the event video and transcript. Check it against the source ↓