Change order updates completion date for Clark County bridge contracts

Nov 4, 2026

The county was asked on Nov. 4, 2026 to authorize Change Order No. 2 with The Ohio Bridge Corporation dba U.S. Bridge to extend the contract completion date to June 25, 2027 for three bridge projects; the change carried no additional dollar cost and the contract total listed was $1,437,395.00 funded from local MVGT funds.

The full story

The Board of Clark County Commissioners was scheduled on Nov. 4, 2026 at 5:30 p.m. in Springfield to consider Change Order No. 2 for bridge work performed by The Ohio Bridge Corporation dba U.S. Bridge, per a request from the County Engineer. The change order updated the project schedule and did not add cost to the contract.