Council packet included change order request adding about $312,000 to Dixie Well drilling contract

Nov 10, 2026

Engineering requested additional construction funds for Dixie Well drilling after unforeseeable subsurface conditions required switching to cable‑tool drilling and advancing 28" casing; the packet lists an additional $312,134.25 (and also includes a later page showing $315,176.00) and says the work is funded by Culinary Water Impact Fees.

The full story

Engineering staff asked the council to approve additional funds for the Dixie Well Drilling Project contract with Hydro Resources - Rocky Mountain, Inc., citing unforeseen subsurface conditions that created a void in unstable gravely soil. The packet explains continuing with the rotary rig would be unsafe; Hydro Resources proposed removing the rotary rig, using a cable‑tool rig to extend 28" casing to approximately 185 feet, then returning the rotary rig to drill to design depth. The change in method also required moving the rig off site and engaging subcontractors.