Courthouse renovation presented $277,173.67 pay application and near‑completion update
Nov 3, 2026
Nov 3, 2026
Turner Construction’s Application for Payment No. 19 requested $277,173.67 for the Dallas County Courthouse renovation (period ending Oct. 31, 2026); an October project summary in the packet reported the project roughly 96% complete and listed Nov. 9 as Level 3 owner-occupancy/first day of court for Courtroom 301.
The full story
A staff report to the Dallas County Board of Supervisors said Turner Construction Company submitted Application for Payment No. 19 for the Dallas County Courthouse renovation requesting $277,173.67 for work through Oct. 31, 2026. The architect said it had reviewed the contractor’s backup and certified the amount for payment to the contractor.