Pentecostal Bridge deck work awaits concrete test results

Aug 11, 2026

Commissioner Dale Logan said concrete in the first part of the bridge deck was not testing properly, although it passed checks coming off the truck. The contractor expected to meet the testing requirements within 28 days; the second half of the deck will wait.

The full story

Work on the Pentecostal Bridge deck is delayed while concrete used in the first portion undergoes testing, Commissioner Dale Logan reported to the Osage County Commission on Aug. 11.